Sewage Works in Rhu:UPDATED
Added on 22 May 2017
Latest information from Scottish Water
- The work scheduled for April this year will now not take place until August.
- The work will be phased over 9 months.
- Service diversion works are required to be carried out prior to the main phase of construction.
- Scottish Power Energy Networks (SPEN) have completed the power diversion
- it is anticipated that Scottish Gas Networks (SGN) will start their diversion work in July.
The following documents were posters on display at the community meeting held in February this year. Note that the dates have changed!